[বিধি ৭৮(৭) দ্রষ্টব্য] OPEN TENDERING METHOD
Columns: Key Action | Key Time Line | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • Open Tendering Method Approved in Procurement Plan — No → Discuss with HOPE or an authorized officer (Notes), then back; Yes → Follow Open Tendering Method
Tender Preparation
  • Prepare specification of object of Procuremnet
  • Prepare an official cost estimate of the object of Procuremnet — Approving Authority: HOPE or an authorized officer; Notes: To be Kept confidential for opening by TEC duming evaluation
  • Pre-qualification necessary — Yes → Prepare Pre-qualification Document (Optional Activity; Notes: Standard Pre-qualification Document issued by the BPPA shall be used); No → Develop Tender Document on the basis of Standard Tender Documents(STDs) (Notes: STDs Issued by the BPPA shall be used)
  • Prepare Invitation for Tender
  • Optional Activity: Prepare Inviation for Pre-qualification
Tender Issue ,Receipt & Process
  • Advertise Inviatation for Tender
  • Modification of Tender Document necessary — Yes → Modify Tender Document; No → Receive Tenders
  • Receive Tenders
  • Open and Process Tenders — Notes: TOC to be formed Minutes to be taken opening in Presence of at least one member of TEC Open in one location Check for Tender Security
  • Optional Activity: Advertise inviation for Pre-qualification → Clarification of Pre-Qualification Document needned (Yes → Clarification on Pre-Qualification Document; No →) Receive and Evaluate Pre-qualification Documents of Procedure → Notify to Pre-qualified Applicants → Modification of Tender Documents ,If any → Send Invitation for Tender to Pre-qualified Tenderers
Tender Examination ,Evaluation and Approval
  • Examine and Evaluate Tender
  • Extention of Tender Validity period is necessary — Yes → Extend Tender Validity period; No → Forfeit Tender Security is needed
  • Forfeit Tender Security is needed — Yes → Forfeit Tender Security; No → Post-quality the successful Tenderer
  • Post-quality the successful Tenderer
  • Approve Contratct Award — Approving Authority: As per Delegation of Financial Powers
  • Notes: As per Procurement Processing and Approval Procedure Only one TEC will evaluate Process to be confidential
Contract Management
  • Notify Award Contract
  • Sign the Contract — If successful Tenderer Fails to sign the Contract ,select from remaing responsive tenderer → Forfeit Tender Security (Notes: - Use Standard contract from - No Negotiation is Allowed - Performance Security to be taken)
  • Prucure the Object
  • Maintain The Record of Procurement

অংশ-খ

[বিধি ৭৮ (৭) দ্রষ্টব্য] OPEN TENDERING METHOD(NCT WORKS)
Columns: Key Action | Key Time Line | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • Open Tendering Method Approved in Procurement Plan — No → Discuss with HOPE or an authorized officer (Notes), then back; Yes → Follow Open Tendering Method
Tender Preparation
  • Prepare specification of object of Procuremnet
  • Prepare an official cost estimate of the object of Procuremnet — Approving Authority: HOPE or an authorized officer; Notes: To be Kept confidential for opening by TEC duming evaluation
  • Pre-qualification necessary — Yes → Prepare Pre-qualification Document (Optional Activity; Notes: Standard Pre-qualification Document issued by the BPPA shall be used); No → Develop Tender Document on the basis of Standard Tender Documents(STDs) (Notes: STDs Issued by the BPPA shall be used)
  • Prepare Invitation for Tender
  • Optional Activity: Prepare Inviation for Pre-qualification
Tender Issue ,Receipt & Process
  • Advertise Inviatation for Tender
  • Modification of Tender Document necessary — Yes → Modify Tender Document; No → Receive Tenders
  • Receive Tenders
  • Open and Process Tenders — Notes: TOC to be formed Minutes to be taken opening in Presence of at least one member of TEC Open in one location Check for Tender Security
  • Optional Activity: Advertise inviation for Pre-qualification → Clarification of Pre-Qualification Document needned (Yes → Clarification on Pre-Qualification Document; No →) Receive and Evaluate Pre-qualification Documents of Procedure → Notify to Pre-qualified Applicants → Modification of Tender Documents ,If any → Send Invitation for Tender to Pre-qualified Tenderers
Tender Examination ,Evaluation and Approval
  • Examine and Evaluate Tender Must follow rule 98(2)(ka) and (Kha) before applying 98(31) — Approving Authority: As per Delegation of Financial Powers
  • Extention of Tender Validity period is necessary — Yes → Extend Tender Validity period; No → Forfeit Tender Security is needed
  • Forfeit Tender Security is needed — Yes → Forfeit Tender Security; No → Post-quality the successful Tenderer
  • Post-quality the successful Tenderer
  • Approve Contratct Award — Approving Authority: As per Delegation of Financial Powers
  • Notes: As per Procurement Processing and Approval Procedure Only one TEC will evaluate Process to be confidential
Contract Management
  • Notify Award Contract
  • Sign the Contract — If successful Tenderer Fails to sign the Contract ,select from remaing responsive tenderer → Forfeit Tender Security (Notes: - Use Standard contract from - No Negotiation is Allowed - Performance Security to be taken)
  • Prucure the Object
  • Maintain The Record of Procurement

অংশ-গ

[বিধি ৭৯ (২) দ্রষ্টব্য] LIMITED TENDERING METHOD
Columns: Key Action | Key Time Line | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • Limited Tendering Method (LTM) approved in Procuremnet Plan — No → Discuss with HOPE or an authorized officer (Notes); also → Reasons to be stated and Approval of the HOPE is required (Notes); Yes → Conditions of LTM fulfiled
  • Conditions of LTM fulfiled — No → Chose OTM or other methods (Optional Activity); Yes → Prepare specification of object of Procuremnet
Tender Preparation
  • Prepare specification of object of Procuremnet
  • Prepare an official cost estimate of the object of Procuremnet — Approving Authority: HOPE or an authorized officer; Notes: To be Kept confidential for opening by TEC duming evaluation
  • Develop Tender Document on the basis of Standard Tender Documents(STDs) — Notes: Standard Tender Document issued by the BPPA shall be used
  • Prepare Invitation for Tender
Tender Issue ,Receipt & Process
  • Identity limited Suppliers/Prepare a list of qualified potential Tenders — Notes: Selection should be in a non-discriminatory manner and number should be sufficient to ensure effective competition; Optional Activity: -Advertise annually to seek new potential Tenders -Reasons enlisted Tenderers on annual basis
  • Send invitation to lmited Suppliers/Enlisted qualified Tenderers
  • Receive Tenders
  • Open and Process Tenders — Notes: -TOC to be formed -Minutes to be taken -opening in Presence of at least one member of TEC -Open in one location -Check for Tender Security
Tender Examination ,Evaluation and Approval
  • Examine and Evaluate Tender — Approving Authority: As per Delegation of Financial Powers; Notes: -As per Procurement Processing and Approval Procedure -Only one TEC will evaluate -Process to be confidential
  • Extention of Tender Validity period is necessary — Yes → Extend Tender Validity → Forfeit Tender Security; No → Forfeit Tender Security is needed
  • Forfeit Tender Security is needed — Yes → Forfeit Tender Security; No → Post-quality the successful Tenderer
  • Post-quality the successful Tenderer
  • Approve Contratct Award — Approving Authority: As per Delegation of Financial Powers
Contract Management
  • Notify Award Contract
  • Sign the Contract — If successful Tenderer Fails to sign the Contract ,select from remaing responsive tenderer → Forfeit Tender Security (Notes: - Use Standard contract from - No Negotiation is Allowed - Performance Securiy to be taken)
  • Prucure the Object
  • Maintain The Record of Procurement

অংশ-ঘ

[বিধি ৭৯ (২) দ্রষ্টব্য] TWO STAGE TENDERING METHOD
Columns: Key Action | Key Time Line | Main Activity | Approving Authority | Optional Activity | Notes FIRST STAGE
  • Two Stage Tendering Method (TSTM) approved in Procurement Plan — No → Discuss with HOPE or an authorized officer (Notes), then back; Yes → Conditions of TSTM fullfilled
  • Conditions of TSTM fullfilled — No → Choose OTM or other methods (Optional Activity); Yes → Prepare Tender Document
Tender Preparation
  • Prepare Tender Document on the basis of Conceptual design and/or stipulated performance specification using (STDs) — Notes: STDs Issued by the BPPA shall be used
  • Prepare Invitation for Tender
  • Advertise for unpriced technical proposals — Notes: Technical Sub-Committee may be required
Tender Opening & Evaluation
  • Receive, open and process un-priced Tenders — Notes: -TOC to be formed -Minutes to be taken -Opening in Presence of one member of TEC -Open in one location -No tender security is is required
  • Examine & Evaluate Tenders — Approving Authority: As per Deligation of Financial Powers; Notes: Procurement Processing and Approval. - Only one TEC will evaluate. - Process to be confidential
  • No responsive Tender → Reject all Tenders (Optional Activity)
  • Retain Responsive Tenders
Tender Adjustment
  • TEC consult with eachS responsive tenderer on any aspect of the proposal except price — Notes: Consultation be confidential and not be disclosed to completing tenders
  • Review (Approving Authority) → back to TEC consult with each responsive tenderer
  • TEC prepare Individual Minitues of Tender Adjustment
  • Approve Minuted of Tender Adjustment — Approving Authority: As per Deligation of Financial Powers; Notes: Should be kept confidential
  • Yes → Approved Tender Adjustment should be signed by all member of TEC — Notes: - Should be specific with detail specifica-tion & evaluation criteria
SECOND STAGE Final Tender Preparation
  • Modify final Tender Document based on Minitues of Tender Adjustment — Notes: - STDs issued by BPPA shall be used
  • Distribute Tender Document to all responsive tenders to submit best and final Tender — Notes: Priced best and final Tenders
Tender Examination ,Evaluation and Approval
  • Receive Tenders
  • Open and Process Tenders — Notes: -TOC to be formed -Minutes to be taken -Opening in Presence of one member of TEC -Open in one location -Check for tender security
  • No responsive Tender → Review Tender Documents and/or go for retender under (Optional Activity) → back to Modify final Tender Document
  • Examine and Evaluate Tenders — Approving Authority: As per Deligation of Financial Powers; Queries → back to Examine and Evaluate Tenders; Notes: Procurement Processing and Approval. - Only one TEC will evaluate. - Process to be confidential
  • Post-qualify the successful Tenders
  • Approve Contract Award — Approving Authority: As per Deligation of Financial Powers
Contract Management
  • Yes → Notify Award of Contract
  • Contractor/Supplier accept the offer — otherwise → Repeat the process to next lowest (Optional Activity); Yes → Sign the Contract
  • Sign the Contract — Notes: - Use Standard Contract Form. - No Negotiation is allowed - Performance Security to be taken
  • Yes → Procure the object
  • Maintain the Record of Procurement

অংশ-ঙ

[ বিধি ৭৯ (২) দ্রষ্টব্য ] ONE STAGE TWO ENVELOPE TENDERING (OSTETM)
Columns: Key Action | Key Time Line | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • One Stage Two Envelope Tendering Method (OSTETM) approved in Procurement Plan — No → Discuss with HOPE or an authorized officer (Notes), then back; also → Resons to be stated and approval of the HOPE is required (Notes); Yes → Conditions of OSTETM Fulfilled
  • Conditions of OSTETM Fulfilled — No → Choose OTM or other methods (Optional Activity); Yes → Prepare specification of object of procurement
Tender Preparation
  • Prepare specification of object of procurement — Approving Authority: HOPE or an authoried officer; Notes: To be kept confidential for opening by TEC during evaluation
  • Prepare an official cost estimate of the object of procurement
  • Pre-qualification necessary — Yes → Prepare Pre-qualification Document (Optional Activity; Notes: Standard Pre-qualification Document issued by BPPA shall be used); No → Develop Tender Doccument on the basis of Standard Tender Documents(STDs) (Notes: STDs issued by the BPPA shall be used)
  • Prepare Invitation for Tender
  • Optional Activity: Prepare Invitation for Pre-qualification → Advertise Invitation for Pre qualification
Tender issue,Receipt & Process (Key Time Line: Time Table as open Tendering Method)
  • Advertise Invitation for Tender
  • Modification of Tender Document necessary — Yes → Modify Tender Document; No → Receive Tenders
  • Receive Tenders
  • Public Opening only for Technical offer — Notes: -TOC to be formed - Minutes to be taken -Opening in Presence of at least one -Open in One location -Check for Tender Security
  • Optional Activity: Clarification of Pre-qualification Document needed (Yes → Clarification of Pre-qualification Documents; No →) Receive and Evaluate Pre-qualification Documents → Notify to Pre-qualified Applications → Notify to Pre-qualified Applications → Modification of Tender Document ,if any → Send Invitation for Tender to Pre-qualified Tendrers
Tender Examination ,Evaluation and Approval
  • Examine and Evaluate Technical offer — Approving Authority: Approved by Head of the Procureing Entity or Authorised officer; Notes: - Only one TEC will evaluate - Process to be confidential
  • Invite all Tenderers to attend Financial offer
  • Public Opening for Financial offer — Notes: -TOC to be formed - Minutes to be taken -Opening in Presence of at least one -Open in One location -Check for Tender Security
  • Examine Financial offer and Evaluate Tender — Notes: - Only one TEC will evaluate - Process to be confidential
  • Extention of Tender validity period is necessary — Yes → Extend Tender Validity period; No → Forfeit Tender Security is needed
  • Forfeit Tender Security is needed — Yes → Forfeit Tender Security; No → Post -quality the successful Tenderer
  • Post -quality the successful Tenderer
Contract Management
  • Approve Contract Award — Approving Authority: As per Delegation of Financial Powers
  • Notify Award of Contarct
  • Yes → Sign the contract — If successful Tenderer fails to sign the contract ,select from remaining responsive Tenderer → Forfeit Tender Security (Notes: - Use Standard Contract Form. - No Negotiation is allowed - Performance Security to be taken)
  • Procure the object
  • Maintain the Record of Procuremnet

অংশ-চ

[বিধি ৭৯ (২) দ্রষ্টব্য] REQUEST FOR QUOTATION METHOD
Columns: Key Action | Key Time Table | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • Request for Quotation Method (RFQM) approved in Procurement Plan — No → Discuss with HOPE or an authorised officer (Notes); also → Reasons to be stated & approval of the hope is required (Notes); Yes → Conditions of RFQM fullfilled
  • Conditions of RFQM fullfilled — No → Choose OTM or other methods (Optional Activity); Yes → Prepare Quotation
Prepare Quotation
  • Prepare Quotation with details on quality, quantity and delivery time — Notes: Standard Quotation Document Issued by the BPPA shall be used
  • Send Quotations to prospective Tenders — Notes: Request at least 5 Tenderers
  • Receive period Quotation — Optional Activity: If less than 3 Quotation verify with others
Quotation Evaluation
  • Examine & Evaluate Quotations — Approving Authority: As per Delegation of Financial Powers; Notes: Procurement Processing and Approval. - Only one TEC will evaluate. - Process to be confidential
  • Recommend lowest evaluated Tender along with comparative statements — Queries → back to Examine & Evaluate Quotations
  • Approve Contract Award — Approving Authority: As per Delegation of Financial Powers; Yes → Give the purchase order or work oder; No → Choose OTM or other methods (Optional Activity)
Contract Management
  • Give the purchase order or work oder
  • Tenderer confirm purchase order in writing — No → Repeat with Second lowest Tenderer (Optional Activity) → back to Give the purchase order or work oder; Yes → Procure the object
  • Procure the object
  • Maintain the Record of Procurement

অংশ-ছ

[বিধি ৭৯(২) দ্রষ্টব্য] REVERSE AUCTION METHOD 1. Requirement Identification 2. Preparation of Auction Documents
(Technical specs, terms & conditions, evaluation criteria)
3. Supplier Prequalification / Registration 4. Public Invitation for Reverse Auction prices 5. Reverse Auction Setup on E-Platform
(Start time, end time, bid decrement rules, ranking visibility)
6. Auction Start (Suppliers Place Bids Online) 7. Continuous Bidding & Automatic Ranking Display 8. Auction Closing at Deadline (or after no new bids for a set time) 9. Evaluation of Lowest Bid (Check Compliance) 10. Awarding the Contract to Winning Supplier 11. Contract Signing & Execution

অংশ-জ

[বিধি ৭৯(২) দ্রষ্টব্য] DIRECT PROCUREMENT METHOD
Columns: Key Action | Key Time Table | Main Activity | Approving Authority | Optional Activity | Notes Procurement Plan
  • Direct Procurement Method(DPM) approved in the Procurement Plan — No → Discuss with HOPE or an authorised officer (Notes) → Resons to be recorded and approval of the HOPE is required (Notes); Yes → Conditions of DPM fulfied
  • Conditions of DPM fulfied — No → Choose OTM or other methods (Optional Activity); Yes → Prepare Deatails specification
Tender Preparation
  • Prepare Deatails specification of object of Procuremnet as per Rule-38 and identify the Contractor or Supplier
  • Conditions of Rule-76(1)(ka) prevalent — Yes → Issue Notifications of Award (NOA)for procurement of the object (Optional Activity)
  • Develop Tender Doccument on the basis of Standard Tender Documents(STDs) — Notes: Standard Tender Document issued by the BPPA shall be used
Tender Examination ,Evaluation and Approval
  • Examine & Evaluate Quotations — Approving Authority: As per Delegation of Financial Powers; Notes: Procurement Processing and Approval. - Evaluation by Only one TEC - Process shall remain confidential
  • Negotiate with the Tenderer as applicable — Review
  • Approve Contract Award — Approving Authority: As per Delegation of Financial Powers; No → Review (back to Examine & Evaluate Quotations); No → Choose OTM or other methods (Optional Activity); Yes → Issue Notification of Award (NOA)
Contract Management
  • Issue Notification of Award (NOA) — Notes: Use Standard Contract Form
  • Sign the Contract — No → Choose OTM or other methods (Optional Activity); Yes → Procure the object
  • Procure the object
  • Maintain the Record of Procurement

অংশ-ঝ

[বিধি ১২৬ (২) দ্রষ্টব্য] PROCUREMENT OF SERVICES BY QCBS METHOD
Columns: Key Action | Key Time Table | Main Activity | Approval | Optional Activity | Notes Preparation
  • Finalise TOR(Rule 40)
  • Finalise Cost Estimate and Budget (Rule-25(9)) — Notes: To be kept confidential
  • Call for Expressions of Interest (EOI) (Rule-135) — Notes: Formal as per Schedule - 16
Short listing
  • Receipt of EOI (Rule-136)
  • Evalute EOI by PEC (Rule -137)
  • Prepare Shortlist(Rule -137) — Notes: Not less then four(4) Not More then seven(7)
  • If shortlist is less then four(4)
  • Review the assigment and found correct — No → Amend the assigment of asseciatd EOI (Optional Activity) → Re-advertise; Yes → Property advertised
  • Property advertised — No → Re-advertise → Receipt of EOI → Prepare Shortlist → If suitable proposal is again less than four (4) → Finalise Shortlist (Optional Activity) → Approval; Yes → Finalise Shortlist (Rule -137)
  • Finalise Shortlist (Rule -137) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approving authority under the Delega-tion of Financial Powers (If approving authority is below the level of HOPE); Notes: All applicants Participating in the EOI must be informed whether or not they have been short-listed by the procuring Entity
Proposal ,Evaluation, Approval and Contract Award
  • Prepare RFP & Define Evaluation criteria and Minimum Qualifying Mark (MQM) (Rule-139) — Notes: Follow standard RFP,Issued by BPPA
  • Send RFP to the shortlisted consultansts (Rule -139)
  • Receive proposal from consultants (Rule -140)
  • Evaluate Technical Proposal by PEC (Rule-141) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approving authority under the Delega-tion of Financial Powers (If approving authority is below the level of HOPE)
  • Public opening of Financial Proposals of Technical Proposals>MQM(Rule-142) — Notes: Minutes of the public opening must be distributed to all shortlisted consul-tants
  • Evaluate Financial Proposal by PEC(Rule-142)
  • Reject Proposals Whose Eval. Price Exceeds Budget (Rule- 142)
  • Negotiate with Highest Ranking Technical Proposal (Rule -144) — Approval: Approval by approving authority under the delegation of Financial Powers; No → Invite the next highest ranked consultant and so on (Optional Activity) → Approval; Yes → Contract Sign
  • Contract Sign (Rule 147)

অংশ-ঞ

[বিধি ১২৭ (২) দ্রষ্টব্য] PROCUREMENT OF SERVICES BY SFB METHOD
Columns: Key Action | Key Time Table | Main Activity | Approval | Optional Activity | Notes Preparation
  • Finalise TOR(Rule 40)
  • Finalise Cost Estimate and Budget (Rule-25(9)) — Notes: To be kept confidential
  • Call for Expressions of Interest (EOI) (Rule-135) — Notes: Formal as per Schedule - 16
Short listing
  • Receipt of EOI (Rule-136)
  • Evalute EOI by PEC (Rule 137)
  • Prepare Shortlist(Rule 137) — Notes: Not less then four(4) Not More then seven(7)
  • If shortlist is less then four(4)
  • Review the assigment and found correct — No → Amend the assigment of asseciatd EOI (Optional Activity) → Re-advertise; Yes → Property advertised
  • Property advertised — No → Re-advertise → Receipt of EOI → Prepare Shortlist → If suitable proposal is again less than four (4) → Finalise Shortlist (Optional Activity) → Approval; Yes → Finalise Shortlist (Rule-137)
  • Finalise Shortlist (Rule-137) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approving authority under the Delega-tion of Financial Powers (If approving authority is below the level of HOPE); Notes: All applicants Participating in the EOI must be informed whether or not they have been short-listed by the procuring Entity
Proposal ,Evaluation, Approval and Contract Award
  • Prepare RFP & Define Evaluation criteria and Minimum Qualifying Mark (MQM) (Rule-139) — Notes: Follow standard RFP,Issued by BPPA
  • Send RFP to the shortlisted consultansts (Rule -139)
  • Receive proposal from consultants (Rule-140)
  • Evaluate Technical Proposal by PEC (Rule-141) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approving authority under the Delega-tion of Financial Powers (If approving authority is below the level of HOPE)
  • Public opening of Financial Proposals of Technical Proposals>MQM(Rule-142) — Notes: Minutes of the public opening must be distributed to all shortlisted consultants
  • Evaluate Financial Proposal by PEC(Rule-142)
  • Reject Proposals Whose Eval. Price Exceeds Budget (Rule- 142)
  • Negotiate with Highest Ranking Technical Proposal (Rule -144) — Approval: Approval by approving authority under the delegation of Financial Powers; No → Invite the next highest ranked consultant and so on (Optional Activity) → Approval; Yes → Contract Sign
  • Contract Sign (Rule 147)

অংশ-ট

[বিধি ১২৮(২) দ্রষ্টব্য] PROCUREMENT OF SERVICES BY LCS METHOD
Columns: Key Action | Key Time Table | Main Activity | Approval | Optional Activity | Notes Preparation
  • Finalise TOR(Rule 40)
  • Finalise Cost Estimate and Budget (Rule-25(9)) — Notes: To be kept confidential
  • Call for Expressions of Interest (EOI) (Rule-135) — Notes: Formal as per Schedule 16
Short listing
  • Receipt of EOI (Rule -136)
  • Evalute EOI by PEC ( (Rule -137)
  • Prepare Shortlist (Rule -137) — Notes: Not less then four(4) Not More then seven(7)
  • If shortlist is less then four(4)
  • Review the assigment and found correct — No → Amend the assigment of asseciatd EOI (Optional Activity) → Re-advertise; Yes → Property advertised
  • Property advertised — No → Re-advertise → Receipt of EOI → Prepare Shortlist → If suitable proposal is again less than four (4) → Finalise Shortlist (Optional Activity) → Approval; Yes → Finalise Shortlist (Rule -137)
  • Finalise Shortlist (Rule -137) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approv-ing authority under the Delegation of Financial Powers (If approving authority is below the level of HOPE); Notes: All applicants Participating in the EOI must be informed whether or not they have been short-listed by the procuring Entity
Proposal ,Evaluation, Approval and Contract Award
  • Prepare RFP & Define Evaluation criteria and Minimum Qualifying Mark (MQM) (Rule -139) — Notes: Follow standard RFP,Issued by BPPA
  • Send RFP to the shortlisted consultansts (Rule -139)
  • Receive proposal from consultants (Rule-140)
  • Evaluate Technical Proposal by PEC (Rule-141) — Approval: Approval by Head of Procuring Entity or an officer authorized by him/her or an approving authority under the Delega-tion of Financial Powers (If approving authority is below the level of HOPE)
  • Public opening of Financial Proposals of Responsiv Technical Proposals>MQM(Rule-142) — Notes: Minutes of the public opening must be distributed to all shortlisted consultants
  • Evaluate Financial Proposal by PEC(Rule-142)
  • Negotiate with lowerst Eval Price Proposal (Rule -144) — Approval: Approval by approving authority under the delegation of Financial Powers; No → Invite the next highest ranked consultant and so on (Optional Activity) → Approval; Yes → Contract Sign
  • Contract Sign (Rule - 147)

অংশ-ঠ

[বিধি ১৩১ (৮) দ্রষ্টব্য] PROCUREMENT OF SERVICES BY SSS METHOD
Preparation
  • Finalise TOR
  • Finalise Cost Estimate and Budget
  • Prepare RFP
Proposal ,Evaluation ,Approval and Contract Award
  • Issue RFP
  • Receive proposals from consultant
  • Evaluate and Negotiate with the consultant
  • Approval by Approving Authority under the
Uncertain: the box text ends at “under the” in the source (text appears truncated in the printed chart).
  • Contract Award
  • Start the Assignment